Smithtown wharf replacement

Smithtown wharf.JPG

Summary

Smithtown wharf is being replaced. There will be no access to the wharf during the construction period. The boat ramp and parking facilities can be accessed and will be closed periodically only while we launch the barges for piling and installation works. Construction signage and site fencing will be installed to barrier any hazards and give clear direction during the construction works. 

Timeframe

Works are expected to begin in June 2024.

Funding

The project is jointly funded by the NSW Government and Australian Government from natural disaster funding.

Progress to date

August 2023: upon approval of funding, a design and construction contract was awarded.

April 2024: Detailed design complete.

June 2024: Demolition works for removal of existing structure.

July 2024: Commencement and installation of piles.

August 2024: Continued installation of piles and completion of piles. Site works ceased as significant delays for wharf material delivery encountered due to supplier issues.

November 2024: Abutment installation works commence.

December 2024: Abutment installation 30% complete.

January 2025: Council crews take over the project works.

February 2025: Completion of the abutment. Wharf materials obtained. Installation of wharf materials to commence and continue.

Background

Smithtown wharf is at the end of its useful life, and as an essential facility for residents and visitors, its replacement is required.

20240605-Smithtown wharf architect drawing.png

Architect's drawing of the new wharf at Smithtown.

 

20240605-SMithtown wharf 3D.png

3D drawing of the Smithtown wharf.

Location

Smithtown, Smithtown 2440  View Map

Google Map