Support remains a priority for those cut off by Toose Road landslip Published on 18 July 2022 Despite the efforts of Council who are working daily alongside other agencies to reinstate access and support those affected, properties remain cut off on the far side of the Toose Road landslip. Tagged as: , Agriculture, Emergencies and Disasters, Recovery, Roads
An update on the Toose Road landslip: edition eleven Published on 14 July 2022 Progress has again been slow since the last update particularly on the final portion of cut 3. The rock experienced at the top of Cut 3 has been challenging as expected and advised in previous updates. Tagged as: , Agriculture, Recovery, Roads
An update on the Toose Road landslip: edition ten Published on 07 July 2022 Seismic field investigations have occurred with initial feedback received. A concept design is being developed alongside an estimate, which will be included in the long-term options report to be discussed with the community. Tagged as: , Agriculture, Recovery, Roads
An update on the Toose Road landslip: edition nine Published on 30 June 2022 Today’s (June 30) scheduled air resupply has been postponed due to forecasted showers.The pilot is in direct contact with the recipient to coordinate this transport of 30 tonnes of dry feed. Tagged as: , Agriculture, Recovery, Roads
An update on the Toose Road landslip: edition eight Published on 23 June 2022 Resilience NSW has confirmed a bulk feed air resupply for Thursday 30 June. All inclusions have been confirmed.Read more Tagged as: , Agriculture, Recovery, Roads
An update on the Toose Road landslip: edition seven Published on 16 June 2022 Progress has been pleasing since the last update, with our crews able to make significant inroads on Fifes Creek Road. The rock experienced at the top of Cut 3 has been challenging as expected, progress has slowed since hitting the high-strength material however progress continues. Tagged as: , Agriculture, Recovery, Roads
An update on the Toose Road landslip: edition six Published on 09 June 2022 As per previous updates, initial Geophysics investigations have occurred at the slip site using ground penetrating radar. Unfortunately, there was no rock found to 15 metres which confirms a short-term repair solution is not feasible at the slip site. Tagged as: , Agriculture, Recovery, Roads
An update on the Toose Road landslip: edition five Published on 02 June 2022 Progress on the construction of the road has been pleasing since the last update as the weather has allowed works to proceed. Tagged as: , Agriculture, Recovery, Roads
An update on the Toose Road landslip: edition four Published on 26 May 2022 Resilience NSW has confirmed an air supply drop of fodder for Thursday 2 June, utilising a sling to transport bulky goods. Residents will be responsible for the provision of mechanical assistance to load and unload these bulk goods. Tagged as: , Agriculture, Recovery, Roads
An update on the Toose Road landslip: edition three Published on 19 May 2022 The most viable short term access route identified will connect Fifes Creek Road to Toose Road via the Telstra telecommunications tower.Construction progress of this route has been delayed due to the recent rainfall. However, it is anticipated that work will recommence this week with council staff due to inspect the site May 19. Tagged as: , Agriculture, Recovery, Roads
An update on the Toose Road landslip: edition two Published on 12 May 2022 As requested by residents, Council arranged a peer review and second opinion of the geotechnical investigation into the slip site.Regional Geotech Solutions report is attached to this update. The report is based on a detailed field inspection and peer review of the original GHD report. Tagged as: , Agriculture, Recovery, Roads
Toose Road Closure Published on 12 July 2021 Toose Road near Bellbrook will be closed between Wednesday 14 July and Friday 16 July for investigations into a landslip. Tagged as: , Roads