Mid North Coast High Performance Centre

20220901-Mid-North-Coast-High-Performance-Centre-2.jpg

Summary

The Mid North Coast High Performance Centre at South West Rocks will feature a new multi-level grandstand, a function room, amenities and sports training facilities.

Timeframe

Construction began in June 2021 and is expected to be completed in 2022.

The structural aspects of construction and internal fitout have been finished. Landscaping and other works around the new facility are almost complete.

Background and funding

The need for additional sporting and recreational facilities in South West Rocks was identified in the Macleay Valley Sports Strategy in 2017.

The project began as a vision of the South West Rocks Sport and Recreation Committee, with broad support from local sports clubs, community groups, and major regional and state sporting organisations.

Council secured $2,465,268 in funding under the 2018 Regional Sports Infrastructure Fund. The South West Rocks Country Club has also confirmed a contribution of almost $400,000. The additional funds will come from a combination of $1.1 million in grants from the Local Roads and Community Infrastructure Program and a Council contribution $1.19 million.

At its October 2020 meeting, Council selected Lipman Pty Ltd to undertake construction.


Read more about the Mid North Coast High Performance Centre.

  

  