Upgrade of Second Lane and Macleay Valley Way intersection
- Project typeRoad and safety upgrade
- Project value$1,800,000
- Project scheduleApril - August 2024
- Completion Date02 August 2024
Summary
The intersection between Second Lane and Macleay Valley Way is currently being upgraded under the NSW Government's Safer Roads Program.
Proposed features include medians, audio tactile line marking, acceleration and turn lanes, improved super elevation, flexible barriers, and upgrade to existing pavement with asphalt.
The purpose of the works is to improve road safety and reduce road trauma by installing traffic guidance and turn facilities to reduce speed related accidents.
Project cost
Project cost is estimated to be $1,800,000
Project timeline
Project commenced 22 April 2024 and will be completed late July 2024`
Project stages
- Compound installation
- Construction of twin 750 diameter concrete pipes both sides intersection
- Construction pit and two twin headwalls
- Construction new base layer road base Second Lane
- Placement of asphalt as sub base layer pavement
- Construction concrete islands
- Placement of surface layer of asphalt
- Complete shoulder and longitudinal drainage
- Signage and linemarking
- Placement guardrail
Location
Intersection of Second Lane and Macleay Valley Way, Frederickton 2440 View Map
-31.0293747,152.8861894
Intersection of Second Lane and Macleay Valley Way ,
Frederickton 2440
Intersection of Second Lane and Macleay Valley Way ,
Frederickton 2440
Upgrade of Second Lane and Macleay Valley Way intersection