Weekly works update

Each week Kempsey Shire Council prepares a report detailing the work that our infrastructure crews have carried out in the week prior and plan to deliver in the coming week.

Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities

Weekly Works Schedule - Week Ending 26 May 2023
Works Achieved this week  Proposed Works Next Week
Road Construction and Maintenance Program 
Regional Roads – Construction, Rehabilitation & Maintenance
Plummers Lane - Jerseyville Bridge Rehabilitation Plummers Lane - Jerseyville Bridge Rehabilitation
Widening of pavement Widening of pavement
20% complete To continue
Placement of fill Placement of fill
20% complete To continue
Rural Local Roads – Construction, Rehabilitation & Maintenance
Gowings Hill Road, Dondingalong (Blackspot Program) Gowings Hill Road, Dondingalong (Blackspot Program)
Line marking Line marking
Deferred Deferred
Installation of guardrail Installation of guardrail
Deferred Deferred
Airport Road, Aldavilla Airport Road, Aldavilla
Sealing
Complete
Tidying of drains and driveways
Complete
Installation of guardrail Installation of guardrail
Deferred Deferred
Urban Local Roads – Construction, Rehabilitation & Maintenance
Macleay Street, East Kempsey Macleay Street, East Kempsey
Installation of aggline Installation of aggline
25% complete To continue
Sealed Roads – Resealing Program
Works currently in planning. To be delivered at a later date.
Sealed Roads – Maintenance Program
Shire Wide Customer Request Road Register Shire Wide Customer Request Road Register
80% complete - deferred To continue
Barbers Lane
Complete
Cecil Tarrant Drive
Complete
Stuarts Point Streets
Complete
Warne Drive
Complete
Armidale Road
To commence
Unsealed Gravel Re-sheeting Program
Billybyang Road Billybyang Road
70% complete To continue
Smiths Creek Road Smiths Creek Road
5% complete To continue
Unsealed Roads – Maintenance Grading Program
Willi Willi Road Willi Willi Road
25% complete - deferred Deferred
Carrai Road Carrai Road
10% complete - deferred Deferred
Moparrabah Road Moparrabah Road
30% complete - deferred Deferred
Spooners Avenue Spooners Avenue
70% complete To complete
Balls Road Balls Road
10% complete To continue
Back Creek Road
To commence
Roadside Slashing and Vegetation Control Program
Armidale Road Armidale Road
5% complete To continue
West Kempsey Area
Complete
Frederickton Area
Complete
Macleay Valley Way - Kempsey to Frederickton
To commence
Civil Construction Program
Kerb and Gutter Program
Works currently in planning. To be delivered at a later date.
Capital Works Program
Armidale Road Landslip 2 - Armidale Road, Bellbrook Armidale Road Landslip 2 - Armidale Road, Bellbrook
Pavement reconstruction Pavement reconstruction
90% complete - deferred To complete
Footpath Program
Works currently in planning. To be delivered at a later date.
Stormwater Drainage Program
Works currently in planning. To be delivered at a later date.
Traffic Facilities
Signs
Clyde Street Car Park, Kempsey Clyde Street Car Park, Kempsey
No Parking pavement markings No Parking pavement markings
In progress To continue
Macleay Valley Way/Plummers Lane Intersection, Clybucca Macleay Valley Way/Plummers Lane Intersection, Clybucca
Merge lane adjustments Merge lane adjustments
In progress To continue
Crescent Head Foreshore Car Park, Crescent Head Crescent Head Foreshore Car Park, Crescent Head
Line marking Line marking
50% complete - deferred Deferred
Lord Street, East Kempsey Lord Street, East Kempsey
Intersection controls and line markings Intersection controls and line markings
In progress To continue
Various Locations Various Locations
Culvert safety signs Culvert safety signs
In progress To continue
Trial Street, South West Rocks Trial Street, South West Rocks
Parking time limit zone Parking time limit zone
On Hold On Hold
Eden Street, Kempsey Eden Street, Kempsey
Intersection line markings Intersection line markings
In progress To continue
Customer requests/Maintenance Customer requests/Maintenance
Ongoing To continue
Bridge Infrastructure Program
Bridge Replacement Program
Chain O Ponds Bridge, Chain O Ponds Road, Collombatti Chain O Ponds Bridge, Chain O Ponds Road, Collombatti
Installation of bridge warning signs Installation of bridge warning signs
Deferred To commence
Quarry Bridge, Willi Willi Road, Temagog Quarry Bridge, Willi Willi Road, Temagog
Installation of decking units
To commence
Verges Creek Bridge, Verges Creek Road, Verges Creek
Installation of decking units
Complete
Demobilisation from site
Complete
Opening of road to traffic
Complete
Anderbergs Bridge, Temagog Road, Temagog Anderbergs Bridge, Temagog Road, Temagog
Setting up of site Setting up of site
50% complete To complete
Installation of side track Installation of side track
10% complete To complete
Demolition of existing timber bridge
To commence
Kenahs Bridge, Upper Smiths Creek Road, Kundabung
Demolition of existing timber bridge
To commence
Excavation for culvert base slab
To commence
Deep Creek Bridge, Mines Road, Deep Creek Deep Creek Bridge, Mines Road, Deep Creek
Cleaning up of site Cleaning up of site
90% complete - deferred Deferred
Dunbars Crossing Bridge, Nulla Nulla Creek Road, Bellbrook Dunbars Crossing Bridge, Nulla Nulla Creek Road, Bellbrook
Installation of columns Installation of columns
Complete To complete
Installation of abutments and headstocks Installation of abutments and headstocks
Deferred To commence
Smiths Creek Bridge, Smiths Creek Road, Kundabung Smiths Creek Bridge, Smiths Creek Road, Kundabung
Demolition of existing bridge
Complete
Bridge piling Bridge piling
25% complete To continue
Timber Bridge Maintenance Program
Works currently in planning. To be delivered at a later date.
Wharves, Jetties and Footbridges Program
Works currently in planning. To be delivered at a later date.
Open Spaces Program
Parks and Facilities Program
Works currently in planning. To be delivered at a later date.
Sporting Infrastructure Program
Sporting Infrastructure
Works currently in planning. To be delivered at a later date.
Flood Mitigation Program
Flood Infrastructure Renewals Program
Christmas Creek Floodgates, Frederickton Christmas Creek Floodgates, Frederickton
Installation of stairs and new access gate Installation of stairs and new access gate
50% complete To continue
Flood Drain Spraying
Works currently in planning. To be delivered at a later date.
Flood Mitigation Maintenance
Works currently in planning. To be delivered at a later date.
Riverbank Rock Protection Program
Works currently in planning. To be delivered at a later date.
Additional Projects and Other Works
East Street, Crescent Head East Street, Crescent Head
Removal and replacement of stairs Removal and replacement of stairs
70% complete To continue
Sherwood Road/River Street Intersection, Yarravel Sherwood Road/River Street Intersection, Yarravel
Traffic island replacement Traffic island replacement
90% complete To complete
Horseshoe Bay Car Park Refurbishment Horseshoe Bay Car Park Refurbishment
Installation of gravel to sub base levels Installation of gravel to sub base levels
10% complete To complete
Installation of foreshore walkway Installation of foreshore walkway
75% complete To complete
Installation of kerb and gutter
To commence
Shire Wide Shire Wide
Stormwater drainage maintenance Stormwater drainage maintenance
Ongoing Ongoing
Shire Wide - Minor Maintenance Response Shire Wide - Minor Maintenance Response
Customer requests Customer requests
Ongoing Ongoing